Ground base

Overview

Ground base

Air compressors are used to push air into the fuel cell stack. The fuel cell extracts oxygen from the incoming air to enable the reaction at the cathode. In fuel cell systems, the air compressor is also sometimes called an air blower. The performance of a fuel cell system depends significantly on the amount of air available. This makes the compressor one of the most critical components. When used in fuel cell systems it is often critical that the compressor does not introduce any impurities such as oil into the air flow, as this could be harmful to the fuel cells themselves. This is the case for instance in applications with proton exchange membrane fuel cells (PEMFC). There are several ways by which air compressors, or air blowers, can be categorized: e.g. in reciprocating air compressors, centrifugal compressors, and rotary screw compressors.

Countries exports
0 +
Professional Team
0 +

The Other ACM

ECU (included the ACM, H/X, Pump, Valve), (Project NO : TECU101)

Item Specifications Remark
Cooling Capacity Ground Condition : 2.2kW
Flight Condition : 5.5kW
Storage Temperature -57~85℃
Operating
Temperature
-54~85℃ (Start up -40℃)
System Insulation Condensation prevention
H/X Exit Temperature 10~40℃

Development Scope

Development Scope

  • High-Efficiency Compressor Development
  • High Efficiency Turbine Development
  • Performance Test(Compressor, Turbine, ACM)
  • Environment Test(MIL-STD-810F)
  • ACM(Project No : TACM101)

    ECU (included the ACM, H/X, Pump, Valve), (Project NO : TECU101)

    Description Specifications Remark
    ACM Type.• Radial Turbine
    • Centrifugal Compressor
    • Airfoil Bearing
    Flow Rate0.44kg/s
    Rotational Speed 78,853 rpm
    Weight 7kg
    Size 228x408 mm

    Feasibility to Supply the ACM

  • Neuros is always ready to supply an ACM to our customers.
  • You can see the lead time of ACM for case 1 and case in the below table.
  • Item Working ItemTerm Remark
    CASE1Non Development
    (Using Previous Unit)
    Manufacture2 Months Machining/Tooling
    Purchase3 Months Heat Exchanger/Motor/Sensor
    Assembly2 Weeks
    Performance Test 2 Weeks
    Total Delivery 6 Months
    CASE2Development
    (Customizing)
    Design
    2 MonthAerodynamic/mechanical
    Manufacture
    3 MonthsMachining/Tooling
    Purchase Heat 6 MonthsExchanger/Motor/Sensor
    Assembly 2 Weeks
    Performance Test 1 Months
    Environment Test 2 MonthsCould be skipped by customer
    Total Delivery • 10 Months Only ACM & H/X